Construction status

Aggiornato al 8 October 2026

96days since groundbreaking
11%of the way to completion
815days to expected completion
4 July 2026GroundbreakingEnd of 2028Expected completion

The percentage shows the time elapsed between the two official dates, not the technical progress of the works: for that, refer to the diary updates below.

Building site diary

Milestones and updates

  1. 4 July 2026

    Groundbreaking

    Official start date of construction work on The View.

  2. 4 July 2026 · Start of works

    Groundbreaking at The View: work begins on 4 July 2026

    The official start date of construction of the apart-hotel on Praia Cabral beach.

  3. End of 2028

    Expected handover

    Handover of the suites is expected at the end of 2028.